Independent index of public construction bids · Data from CanadaBuys, SAM.gov and USAspending.gov · Refreshed daily · Last update 2026-11-12
United States › Open bids › HI FLAP CR562(1) Kilauea Point

HI FLAP CR562(1) Kilauea Point

Early notice

A Department of Transportation presolicitation for construction work in Kilauea, Hawaii. No response deadline is listed.

AgencyDepartment of Transportation
OfficeFederal Highway Administration · 6982af Central Federal Lands Divisi
Response deadlineNot listed
Posted2026-10-15
Notice typePresolicitation
Set-asideNo Set aside used
Place of performanceKilauea, Hawaii
Solicitation no.6982AF27B000008
CategoryNAICS 237310 · PSC Y1LB

What this notice means

A heads-up that a solicitation is planned. The agency is usually not accepting bids yet, but this is the time to get ready and register.

What the agency is asking for

This is not an invitiation for bid, plan and speficiations are not availble project name: hi flap cr562(1)

Kilauea Point

Project description

Kilauea Point National Wildlife Refuge (KPNWR) is a 203-acre facility located on the north shore of the Island of Kaua'i. It is part of the Kaua'i National Wildlife Refuge Complex managed by the United States Fish and Wildlife Service.

To keep up with the visitation demands, the KPNWR and the USFWS along with the Federal Highway Administration Central Federal Lands Highway Division is proposing to improve the area by providing better access along Kolo Road and Kilauea Road (Route 562) for pedestrians and bicyclists, as well as improvements to the overlook.

The project consists of installation of a sidewalk adjacent the existing roadway from the intersection of Kuhio Highway to the KPNWR Overlook. Work includes pavement rehabilitation and resurfacing of the existing roadway, with full depth pavement on aggregate base course for roadway widening segments, and reconstruction of the existing turnaround.

Guardrail, sidewalk, curb, gutter, two mini-roundabouts, striping, and pedestrian crossings will be provided to establish a safe and accessible corridor for pedestrians and bicyclists. Minor utility adjustments and construction is also anticipated. The total project length is approximately 1.70 miles.

Principal work items

18,500 square yards of Removal of Pavement, Asphalt 3,370 cubic yards of Roadway Excavation 2,900 ton of Roadway Aggregate, Method 2 4,200 ton of Asphalt Concrete pavement, Type 1 630 square yard of minor concrete Pavement, Reinforced 1,540 linear feet of Curb, Concrete, 16-Inch Depth (Slotted) 5,670 square yards of Sidewalk, Concrete 34 Accessibility Ramps, Concrete

Anticipated schedule

Advertise: End of October or Early November 2026 Bid Opening: December 2026 Award: January 2027 Construction: January 2027 January 2028

Estimated cost range: The anticipated cost range is between 10,000,000 and $20,000,000.

View the official notice on SAM.gov →

Bids are submitted through the channel named in the official notice. BidsNear does not accept bids.