U72 Biolab Ventilation and Vestibule Upgrade / U72 Fuselage Outdoor Upgrade
ClosedNational Research Council Canada sought bids for this general construction requirement in National Capital Region. Open bidding: any qualified supplier can submit a bid. Bidders had 28 days between publication and closing.
Key dates
- Published July 23, 2024 843 days ago
- Bids close August 20, 2024 815 days ago
- Contract starts August 20, 2024 815 days ago
- Contract ends February 28, 2025 623 days ago
Work is expected to start about 0 days after bids close. Planned duration: about 6 months.
What the buyer is asking for
24-58079 U72 Biolab Ventilation and Vestibule Upgrade / U72 Fuselage Outdoor Upgrade
You are invited to submit one electronic Technical Proposal and one electronic Tender Form in two separate attachments to fulfil the following requirement forming part of this Request for Proposal. One attachment must be clearly marked ‘Technical Proposal’ and the other attachment must be marked ‘Tender Form’.
All financial information must be fully contained in the Tender Form, and only in the Tender Form. Vendors who provide financial information in the technical proposal will be disqualified.
The National Research Council Canada, 1950 Research Private Ottawa, has a requirement for a project that includes:
The proposed scope of work includes the upgrade of the modular building, the installation of a new access platform, installation of a new boiler, installation of an existing Air Handling Unit located at Building U72 at the Upland Campus of the National Research Council of Canada.
Show the full description
Tender Destination
a) Tenders are to be submitted by email only: National Research Council Canada
NRC.BidReceiving-Receptiondes Soumissions.CNRC@nrc-cnrc.gc.ca
Endorsed “Tender for (insert title of work as it appears in the drawings and specifications)” and must bear the name and address of the tenderer.
b) Unless otherwise specified, the only documents required to be submitted with the tender are the Tender form and the Bid Security.
Selection Criteria
Potential bidders will be rated in a combination of technical score and price rating. For this project the total score will be established as follows:
Technical rating 40% = Technical Score (Points) Price rating 60% = Price Score (Points) Total Score = Max. 100 points
Mandatory requirements
Failure to meet the mandatory requirement will render the proposal as non-compliant and no further evaluation will be carried out.
Item Mandatory Criteria Proposal Page #(s) 1 The Proponent must have a minimum of ten (10) years’ experience in the execution of mechanical project, and as a contractor providing construction services comparable to this tender. Provide a company profile and relevant history as described in item #1 of the evaluated technical criteria.
2 The Proponent must supply a CV for the proposed construction site supervisor. The proposed construction site supervisor must possess a minimum of 7 years’ experience in contract/construction supervision, as a site supervisor or similar position. Two pages (letter size) maximum for this criteria. 3 The Proponent must supply a CV for the proposed construction Project Manager.
The proposed project Manager must possess a minimum of 7 years’ experience in contract/construction administration, as a Project, Manager or similar position. Two pages (letter size) maximum for this criteria.
Include this table with your proposal and indicate the proposal page where the information can be found.
Any Proposal which fails to meet any of the following mandatory requirements will be considered non-compliant and will not be given further consideration. Each requirement should be addressed separately.
Evaluated Technical Criteria
Item Evaluated Technical Criteria Proposal Page # (s) Max Score 1 Demonstrated experience by the Proponent providing general construction services relevant to this project. Include 2 comparable projects completed by the proponents firm in the last 10 years with reference names & phone numbers. Maximum 1 page per project.
Evaluations will take into account relevance compared to the scope of this tender (up to 3 point for each example project) and whether the reference was satisfied with the work completed (up to 1 point for each example project).
It is the responsibility of the bidder to ensure the contact information for the reference is accurate and available to provide feedback in less than 48Hres. If the reference cannot be reached or declines to provide input the proponent will receive a score of 0/1 for that example. 8 2 Qualifications and overall experience of proposed construction site supervisor.
The proposed construction site supervisor must possess a minimum of 7 years’ experience, CV will be scored on the basis of related experience (up to 4 points), experience acting as a construction site supervisor on federal government construction projects (up to 3 points). Include detailed examples of 2 past projects. CV should be no longer than 3 pages.
6 3 Qualifications and overall experience of proposed construction Project Manager. The proposed project Manager must possess a minimum of 7 years’ experience. CV will be scored on the basis of related experience (up to 3 points), experience acting as a construction site supervisor on federal government construction projects (up to 2 points).
Include detailed examples of 2 past projects. CV should be no longer than 3 pages. 6 4 The Proponent must provide their construction schedule for this project, from award to final completion, detailing major milestones, critical path elements, and associated timelines.
Schedule evaluation will be based on whether it meets the completion date noted in the tender documents (up to 2 point), and if the tasks and associated timelines demonstrate the contractor understands the scope of work (up to 3 points). Contractor must flag any issue with long lead items into their schedule and possible delay if any. 5 Total 25
Include this table with your proposal and indicate the proposal page where the information can be found.
Evaluation and Rating
Financial Proposal will remain sealed and only the technical components of the proposals considered responsive will be reviewed, evaluated and rated by an NRC Evaluation Board in accordance with the criteria listed in the evaluated technical criteria table.
No further consideration will be given to proponents not a
Who can bid and how it is decided
- Process Competitive - Open bidding Open bidding: any qualified supplier can submit a bid.
- Trade agreements Canadian Free Trade
- Goods & services category General building construction, HVAC mechanical construction service
Documents attached to the notice
- 24 58079 tender package english 0PDF · official file
- 6314 u72 fuselage drawings ift englishPDF · official file
- 6283 u72 biolab dwgs ift englishPDF · official file
- 6283 u72 biolab specs ift englishPDF · official file
- 6314 u72 fuselage specs ift englishPDF · official file
- 24 58079 addendum no. 1 photo1PDF · official file
- 24 58079 addendum no. 2PDF · official file
- 24 58079 addendum no. 1 photo2PDF · official file
- 24 58079 addendum no. 1PDF · official file
View the official notice → (reference cb-273-4862203)
This tender is closed. See open general construction tenders.
More general construction tenders in National Capital Region
- Replacement of Steam CoilsCanadian Food Inspection Agency (CFIA) · Closed
- APN - 1495 Heron Road - Site Servicing ServicesBuild Canada Homes · Closed
- Replacement of Motor Control Centres at the Radiation Protection BureauDepartment of Public Works and Government Services (PSPC) · Closed
- EP076-270289 Sir Frederick Banting Building Fire Alarm System ImprovementsDepartment of Public Works and Government Services (PSPC) · Closed
- Building of the Snowflake KingdomDepartment of Canadian Heritage (PCH) · Closed
- Installation of a Permeable Reactive Barrier at 335 River Road, OttawaDepartment of Public Works and Government Services (PSPC) · Cancelled
National Research Council Canada has 75 tenders in our database, typically open for about 28 days. See the buyer profile →
Other tenders from National Research Council Canada
- M19 Corridor 102Closed · 2025-03-17
- Renovation of Rooms 252A and 230 of Building U-66Closed · 2025-03-11
- Modernization of a High-Pressure Aluminum Die Casting Process ControlClosed · 2025-02-24
- Replacement of Light FixturesClosed · 2025-02-20
- Washrooms Renovation of Building U-66Closed · 2025-02-14